NEWS AND ACTIVITIES (in reverse chronological order)
October 2008
The US Army Corps of Engineers (USACE) Hydrologic Engineering Center (HEC) began work on the "HEC-RAS into CHPS" project, recently announcing that their contractor has completed a first version of the Java library needed by Deltares. Things are going well and are on schedule.
The task order for RTi was awarded, enabling Deltares to formally begin work on the adapter and conduct testing. NERFC provided RTi/Deltares with a working version of HEC-RAS for testing.
HSMB is investigating two approaches to implementing HEC-RAS models at RFCs: one is to convert existing FLDWAV/DWOPER models; the other is to get existing USACE models and implement those. The HSMB task, scheduled to complete in January 2009, is on track.
July 2008
The only impediment to Phase 2 (implementation) of the U.S. Army Corps of Engineers (USACE) Hydrologic Engineering Center’s River Analysis System (HEC-RAS) project now involves contracts. Deltares is waiting for authorization from NOAA Procurement to proceed; funds for HEC were transferred at the end of June; HEC will notify OHD when they can begin work
April 2008
Deltares and OHD traveled to LMRFC in February to discuss functional requirements for the HEC-RAS capability in CHPS. OHRFC also attended. The Deltares-OHD team then traveled on to Davis, CA to meet with USACE HEC and its contractor Resource Management Associates (RMA); RMA is the contractor that built the Corps Water Management System (CWMS) in collaboration with HEC. The goal of the meeting in Davis was to discuss potential solutions.
Deltares, HEC, and LMRFC came to an agreement concerning the overall technical solution, which allowed Deltares to draw up a proposal for review on March 25.
Phase 1 (design) of the project is now complete. Phase 2 (implementation of the proposed solution) is expected to begin once contract tasks are in place for Deltares and HEC.
With the decision that OHD will discontinue support for FldWav, the transition of forecasting operations from FldWav to HEC-RAS is now a CHPS operational capability pre-requisite.
January 2008
Phase 1 of the project began with a kick-off conference call in December where a proposed project schedule was discussed. The project team consists of the following members:
- Delft (Deltares) as the overall software project lead.
- LMRFC (David Welch, Dave Ramirez) will provide the RFC forecaster perspective, as well as technical support for potential use of local applications. [Note: OHD has also contacted OHRFC to request their participation on the team.]
- HEC will identify the level of effort required to port their existing Sun Solaris-based RAS software to Linux.
- OHD HSMB will represent OHD's requirements for getting RAS into operations as a replacement for FldWav.
- OHD HSEB will monitor the contract task with Apex (mechanism used to access Deltares), and also the MOA between HEC and OHD.
Deltares plans to travel to the U.S. at the end of February to meet with HEC, OHD, and LMRFC, and begin the process of prototyping/designing a solution.
Phase 2 of the project - implementation of the final solution - is expected to begin later this FY.
[Back to Top]
October 2007
The goal of this project is to provide RFCs with access to the USACE HEC River Analysis System (HEC-RAS) via CHPS (not NWSRFS). HSEB anticipates two phases, the first of which (Phase 1) will be the solution design; this piece has now been contracted out to Delft. The solution is expected to leverage much of the CHPS-based software developed on the ResSim project, without the connection to NWSRFS.
Also this quarter NOAA and the USACE finalized an updated Memorandum of Agreement (MOA) between the two agencies, thereby providing a vehicle to fund HEC's contributions to Phase 1 of this project. Funding is also now secured. With agreements, contracts, and funding in place, all that remains is for HEC to complete other unrelated commitments and release their staff to begin Phase 1.
The second phase, implementation of the design, will require HEC and other HSEB contractors (to be determined) to implement the proposed software design into CHPS.
July 2007
After a series of discussions with HSMB and HEC, HSEB began the necessary paperwork to begin the task of incorporating the USACE HEC River Analysis System (HEC-RAS) into CHPS. HSEB anticipates two phases, the first of which will be the solution design; this piece will be contracted out to Apex. The second phase, implementation of the design, will require HEC and possibly others to develop additional software. The solution is expected to leverage much of the CHPS-based software developed on the ResSim project.
|